U.S. Army Corps of Engineers, Afghanistan Engineer District via Technologists, Inc.
ANA Logistics Facilities (Phase II)
Buildings, stone walls and paved roads for the Afghan National Army logistics headquarters. The Corps of Engineers recognized TCL's work here together with the CMA project.
Scope of work
- Buildings and barracks
- Stone walls, including the wall around Building 12
- Culverts and drainage
- Grade and gravel
- Steel doors, fuel tank and water tank
- 3 km of asphalt roads and vehicle parking
Contract value and completion date (25 Oct 2007) from TCL's 2010 fact sheet.
From the site
2 photosSigned agreements
3 on file| Agreement no. | Work | Amount | Effective |
|---|---|---|---|
| Ti-23/Option 5/ANA Ph-II/05 | Paved roads, grade, gravel and vehicle parking lots (cost plus fee) | Ceiling $150,000 | 25 Oct 2005 |
| Ti-45/CSW/ANA Ph-II/06 | Stone wall around Building 12 | $25,817.90 | 25 Oct 2005 |
| 01/Road Asphalt/ANA-II and CMA/05 | Road asphalt for ANA-II and CMA, issued by TCL to its own paving subcontractor | $315,540.50 | 27 Nov 2005 |
Amounts as written on each signed agreement. "Ceiling" marks a task-order agreement where the final billed amount depended on work ordered.